A full rewire replaces the wiring throughout the house, including the sockets, lights and consumer unit (fuse box) that the quote covers, then tests and certifies the installation. A partial rewire replaces only the circuits that need it and leaves sound circuits in place. Swapping the consumer unit on its own can be enough if testing shows the existing cables are sound and the main problem is an old board. The only reliable way to choose is an inspection and test by a qualified electrician, not the age of the house or a photograph of the fuse box.

Why we’re writing this

We’re an electrical contractor and we do rewires, so we have an interest in this question. That’s why we’ll tell you when a full rewire is more than you need, when a partial job would only delay the problem, and when a new consumer unit plus some repairs would do. If you only want the cheapest possible “rewire”, or a price before anyone has seen the property, we are probably not the right firm.

The four options, side by side

OptionWhen it usually fitsWhat it involvesWhat it does not do
Inspection and test (EICR)You don’t know the condition, or you’re buying or renting the property outA written report on the installation, with codes for anything that needs attentionIt does not replace any cables
Repairs or a new consumer unit onlyTesting shows the cables are sound, and the faults are specific — or the board itself is the weak pointFix the reported faults, and/or fit a modern consumer unit, then retestIt does not make old or damaged cables safe
Partial rewireSome circuits are old or faulty and the rest test as satisfactoryReplace only those circuits (for example a kitchen, an extension, or upstairs lighting), and leave sound circuits in placeIt does not renew wiring you have chosen to leave. If that wiring is of a similar age, you may face the same decision later
Full rewireOld or damaged cable throughout, or widespread faults that a few circuit replacements would not solveNew cabling, the fittings the quote includes, a new consumer unit, then testing and certificationIt is more disruption than a smaller job. It is the wrong answer if only part of the installation is poor

This matches the shorter comparison we already publish on how to tell if your house needs rewiring and in the house-rewire FAQs. The sections below unpack each option, including when a consumer unit swap alone is enough.

When a new consumer unit (fuse box) is enough

A consumer unit is the board that divides the supply into circuits and houses the protective devices. Older boards may use rewireable fuses, or lack the residual-current protection expected on a modern installation. Fitting a new board can improve how faults are detected and how quickly a circuit is disconnected. It is not a rewire. Replacing a consumer unit is itself notifiable work in England and Wales, even if you are not rewiring the house.

A consumer unit swap on its own is worth discussing when:

  • An electrician has tested the existing circuits and found them satisfactory, or found only a small number of faults that can be repaired without replacing whole runs of cable.
  • The visible problem is the board itself — for example a wooden or brown plastic box, rewireable fuses, or a board with no residual-current protection — rather than damaged cable throughout the house.
  • You need better protection now, and the rest of the installation does not justify opening up floors and walls.

It is not enough when the cables themselves are in poor condition. Rubber or cloth-covered insulation that has gone brittle, scorched fittings, repeated trips with nothing plugged in, or an EICR that finds widespread problems with the wiring, all point past the board to the circuits behind it. A new consumer unit on old cable can give a false sense of safety: the protection is better, but the cables have not changed. See also signs your consumer unit may be outdated and our guide to rubber cables.

The technical judgement — whether a particular board and set of circuits meet current requirements — has to be made by a qualified electrician on site. We will not diagnose that from a photograph.

When a partial rewire makes sense

A partial rewire replaces one or more circuits and leaves the rest. Typical cases are a kitchen that is being stripped back, an extension or loft conversion that was wired to an older standard, a single lighting or socket circuit that has failed testing, or a house where one floor was rewired years ago and the other was not.

The honest trade-off is this: you spend less time and disruption on the parts that are already sound, but you keep whatever you did not replace. If most of the wiring is of a similar age and type, a partial job can mean coming back to do the rest in a few years, with another round of lifted floors and making good. If testing shows a clear split — for example the downstairs sockets are poor and the rest are satisfactory — a partial job is often the straight answer, not a compromise.

Ask any electrician to say, in writing, which circuits they would replace, which they would leave, and why. Two “partial rewire” quotes only compare if they cover the same circuits.

When a full rewire is the right job

A full rewire is the right scope when the cables are old or damaged throughout, or when so many circuits would need replacing that leaving a few would not save you much disruption. NICEIC describes a house rewire as removing old, outdated or faulty cabling and installing modern replacements, either across the whole home or in certain locations, and notes that the work often includes replacing the consumer unit and, if you ask for it, moving or adding sockets, switches and lights. That is the difference between “renew what is there” and “redesign how the house is used” — extra points and relocated fittings should be in the quote if you want them.

A full rewire is more disruption than a board change or a single-circuit job. Floors are lifted, some walls may be chased, and rooms are without power at times. We have written separately about how long a rewire takes and whether you can live in the house. Plastering and decorating are separate jobs and are not included unless the quote says so.

What should be in writing before you choose

  1. The evidence. An EICR, or the findings of a survey, that says what is satisfactory and what is not. Age alone is a clue, not a verdict.
  2. The scope. Full, partial (named circuits) or consumer unit and listed repairs.
  3. What is included. Cables, sockets and switches, the consumer unit, testing, certificates, and any making good. What is not included should be just as clear.
  4. The finish. Who makes good chased walls and lifted floors, and whether plastering or decorating is in or out.
  5. Like for like. A cheap quote that leaves circuits out, or skips testing and certification, is not the same job as a full certified rewire.

We don’t publish a fixed rewire price, because the scope is the price. We survey first, then give a written quote. There is a separate article on what changes the price of a house rewire.

Local notes: Stockport, Manchester and Blackpool (FY)

The houses we see across SK (Stockport), M (Manchester) and the FY towns we cover — including Blackpool, Lytham St Annes, Fleetwood and Thornton-Cleveleys — often have wiring of more than one age. A kitchen or extension may have been redone, while the original circuits remain elsewhere. That is exactly the situation where a partial rewire can be right, and also where a cheap “full rewire” quote may have quietly left those newer circuits out, or a cheap “board only” quote may have ignored older cable still in the walls. An inspection should say which you have, not assume from the postcode or the year the house was built.

Who this isn’t right for

  • If you need a price before anyone sees the property. We don’t publish a fixed rewire price. We survey first, then give a written quote.
  • If you want a full rewire when testing would show a smaller job is enough. We would rather talk you out of work you don’t need than sell you the largest quote.
  • If you want the cheapest possible “just change the fuse box” without testing the cables. A new board on untested old wiring is not a job we will treat as finished.
  • If you only need a single fault repaired. A dead socket is often a local repair, and a smaller call-out may be the quicker option.
  • If you’re outside our areas. We mainly work in SK (Stockport), M (Manchester) and some FY postcodes.

How FCR does it

FCR has over 30 years’ experience. We are a NICEIC Approved Contractor and an ECA member. Our work carries a 12-month workmanship guarantee with unlimited claims during those 12 months, and we hold £5M public liability insurance. This is in addition to your statutory rights. Customers rate us 4.9 stars from 90 Google reviews, as at November 2026. We’ll tell you what we find and what we’d recommend, including when a consumer unit change, a partial rewire or simply a test is enough.

FAQs

Can a new fuse box replace the need for a full rewire?

No, not on its own. A new consumer unit improves protection, but it does not replace damaged or unsuitable wiring. If testing shows the cables are sound, a new board plus any listed repairs can be the right job. If the cables are poor throughout, you still need those circuits replaced. A qualified electrician should explain the evidence before you decide.

What’s the difference between a partial rewire and a full rewire?

A full rewire replaces the wiring throughout the house, including the sockets, lights and consumer unit that the quote covers. A partial rewire replaces only the circuits that need it — for example an old kitchen circuit or upstairs lighting — and leaves sound circuits in place. If most of the wiring is old, a partial job can leave you with the same problem later.

Does the age of my house mean I need a full rewire?

No. Age is a clue, not a verdict, and there is no legal rule that a house must be rewired at a particular age. NICEIC’s homeowner guide, citing Electrical Safety First, says that if a property is over 30 years old and still has its original wiring, it likely will need updating to meet modern standards, including replacing the fuse box or older consumer unit. Electrical Safety First’s own advice also says there are no set guidelines for when a property should be rewired, and that old wiring is not automatically unsafe. The way to know is an inspection and test, not the year on the title deeds.

Is a rewire notifiable work?

In England and Wales, installing a new circuit and replacing a consumer unit are notifiable work under Part P of the Building Regulations. A house rewire typically includes both, so it is notifiable. A contractor registered on a competent person scheme, such as a NICEIC Approved Contractor working within that scheme, can self-certify the work and arrange the notification for you. If the electrician is not registered that way, the work has to be notified to building control, or checked by a registered third-party certifier, before it starts. You should receive an Electrical Installation Certificate (EIC) to BS 7671 for a rewire or consumer-unit replacement, and a Building Regulations compliance certificate when the work is notified through the scheme. A Minor Electrical Installation Works Certificate is only for certain alterations to an existing circuit, not for a full rewire. Ask for the certificates in writing before work starts.

Will a partial rewire still make a mess?

Yes, in the rooms and routes that circuit uses. Floors may be lifted and some walls may be chased along those runs. A partial job is usually less disruption than a full rewire, but it is not dust-free. Plastering and decorating are separate unless the quote says otherwise.