A house rewire typically takes from a few days to a week or two, depending on the size of the property, how easily the cables can be reached, and whether you are living in the house. Industry guides put a full rewire in a similar band: often around 5–10 days for the electrical work, not including plastering or decorating, with smaller homes at the shorter end and larger or more complicated ones at the longer end. You can usually stay living in the house, but it is slower, dustier and means some rooms will be without power at times. These are typical figures, not a promise for your home — an electrician should confirm the plan at the survey.
Why we’re writing this
We’re an electrical contractor and we do rewires, so we have an interest in this question. People often ask us two things at once: how many days it will take, and whether they have to move out. We’ll answer both honestly, including the mess and the limits of staying put. If you need a guaranteed number of days before anyone has seen the house, or a job with no dust and no lifted floors, we are probably not the right firm.
Typical timescales (industry figures, not a quote)
NICEIC’s homeowner guide says a rewire can take “anything from a few days to a week or two depending on the size and complexity of the project”, and that a registered electrician can give a more accurate estimate when quoting for your property. Checkatrade’s July 2026 guide gives a tighter starting point for the electrical work only, before any finishing decoration:
| Situation | Typical industry range | Source |
|---|---|---|
| Full house rewire, electrical work only | Around 5–10 days (Checkatrade also describes a wider “4 to 10 days” band) | Checkatrade, updated July 2026 |
| Two-bedroom house | Generally 4–5 days | Checkatrade, updated July 2026 |
| Three-bedroom house with two bathrooms | Typically 6–10 days | Checkatrade, updated July 2026 |
| Any size or complexity | A few days to a week or two | NICEIC homeowner guide |
| Plastering and decorating afterwards | Not included in the figures above | Both sources treat finishing as separate |
Treat those numbers as a starting point, not a timetable for your house.
What FCR has said about empty homes
In our experience, the electrical work on an empty home often takes around 4–5 days. That is a working guide from our own jobs, not a promise for every house. A lived-in home takes longer and is done in stages. We will give you a plan for your property at the survey rather than invent a standard extra-day figure here.
Can you live in the house while it’s done?
Yes, many people do. NICEIC says you can live in the house during a rewire, but it may make the project more difficult and costly, because the electrician has to work around you. Expect furniture to be moved, floorboards to be lifted, some cutting into walls, noise and dust, and power to be off in specific rooms — or sometimes more widely — for stretches of the day so the wiring can be removed and replaced safely.
In practice that usually means:
- You can often keep living there, especially if you can treat one or two rooms as out of bounds each day.
- You will not have a normal house for that week. There will be dust, tools, lifted floors and limited power. Kettles, working from home, medical equipment and young children all need a frank conversation before we start.
- Power is isolated to work safely. We plan room by room where we can, so the whole house is not left dark all week, but you should not rely on every circuit being available all day.
- An empty house is quicker. No furniture to work around, and we can open more than one area at a time.
If your house was built or refurbished before 2000, some finishes that a rewire may disturb — for example certain floor tiles, textured coatings or older loft materials — can contain asbestos. The legal duty to manage asbestos under the Control of Asbestos Regulations 2012 (regulation 4) applies to non-domestic premises and to the common parts of multi-occupied domestic buildings, not to a private homeowner in their own house. Even so, tell us before we quote if you know or suspect asbestos is present, and we will discuss whether a survey is needed.
If anyone in the household depends on electricity for medical equipment, tell us before we quote. A rewire is not something to improvise around life-critical kit. See also our shorter companion page, can you live in your home during rewiring?.
What actually takes the time
NICEIC notes that the same things that change the cost of a rewire usually change how long it takes. In our experience the main drivers are:
- The size of the house and the number of points. More rooms, more circuits, more sockets and lights.
- Whether the house is lived in or empty. A lived-in job is staged so you can still use parts of the house.
- Access. Fitted kitchens, loft hatches, floor finishes and furniture all slow first-fix work.
- The building itself. Solid walls, awkward voids and later extensions take longer than a straightforward empty shell.
- The scope. A full rewire takes longer than a partial rewire or a consumer unit change. If you are still deciding the scope, start with full rewire, partial rewire or just a new fuse box.
- Testing and certification at the end. This is not optional extra time. A rewire in England and Wales is notifiable work under Part P of the Building Regulations; you should receive the certificates when the job is finished.
- Making good after the electricians leave. Plastering and decorating are separate jobs and are not included unless the quote says so. They sit outside the day-counts above.
How to prepare if you are staying
NICEIC’s practical advice is a good checklist: make the consumer unit, sockets, switches and light fittings as accessible as you can; move furniture away from walls; cover what you cannot move; empty cupboards that hide cables; take decorations off the walls you know will be opened up; and decide in advance where you want extra sockets or lights, so those decisions are not made mid-job.
We would add: agree which room is “home base” each day (somewhere you can boil a kettle and charge a phone), and talk through pets, parking and working-from-home before the start date. Changing socket positions once first-fix has begun is one of the easiest ways to add a day.
Local notes: Stockport, Manchester and Blackpool (FY)
Across SK (Stockport), M (Manchester) and the FY towns we cover — including Blackpool, Lytham St Annes, Fleetwood and Thornton-Cleveleys — the houses we rewire are often occupied family homes rather than empty shells. That is why a lived-in, staged plan comes up so often. Older terraces and semis can also hide mixed-age wiring and tighter floor voids, which is another reason two houses with the same number of bedrooms do not take the same number of days. The survey is where we pin that down for your property, not a blog post.
Who this isn’t right for
- If you need a guaranteed number of days before anyone has seen the house. We will give you a plan at the survey, not a one-size-fits-all promise from this page.
- If you cannot accept dust, lifted floors or rooms without power during the working day. Staying in is possible, but it is not comfortable, and we will not pretend otherwise.
- If you need the house completely undisturbed because someone relies on a continuous power supply for medical equipment, unless we have first agreed a safe working plan. Tell us before we quote.
- If you want plastering and decorating bundled in without that being written into the quote. Those are separate jobs unless we say otherwise.
- If you’re outside our areas. We mainly work in SK (Stockport), M (Manchester) and some FY postcodes.
How FCR does it
FCR has over 30 years’ experience. We are a NICEIC Approved Contractor and an ECA member. Our work carries a 12-month workmanship guarantee with unlimited claims during those 12 months, and we hold £5M public liability insurance. This is in addition to your statutory rights. Customers rate us 4.9 stars from 90 Google reviews, as at November 2026. At the survey we will tell you whether we think you can stay living in, how we would stage the rooms, and how long we expect the electrical work to take in your house.
FAQs
How long does a rewire take?
It depends on the size of the house and whether you’re living in it. Industry guides suggest anything from a few days to a week or two, often around 5–10 days for the electrical work on a full rewire, not including decoration. In our experience, the electrical work on an empty home often takes around 4–5 days — a working guide, not a promise. A lived-in home takes longer and is done in stages. We’ll give you a plan at the survey.
Do I have to leave the house?
Not always. Many people stay, but expect dust, lifted floors and no power in some rooms at times. NICEIC notes that living in can make the project more difficult and costly, because the electrician has to work around you. We plan the work room by room where we can.
How long does it take to rewire a three-bedroom house?
Checkatrade’s July 2026 guide suggests a typical three-bedroom house with two bathrooms takes 6–10 days for the electrical work. That is an industry starting point, not an FCR quote. Access, whether you are living in, and the exact scope can move a job either way. We will confirm the days for your house at the survey.
Does the day-count include plastering and decorating?
No. The industry figures above are for the electrical work. Plastering and decorating are separate jobs and are not included unless the quote says so.
Is a rewire notifiable work?
In England and Wales, installing a new circuit and replacing a consumer unit are notifiable work under Part P of the Building Regulations. A house rewire typically includes both, so it is notifiable. A contractor registered on a competent person scheme, such as a NICEIC Approved Contractor working within that scheme, can self-certify the work and arrange the notification for you. If the electrician is not registered that way, the work has to be notified to building control, or checked by a registered third-party certifier, before it starts. You should receive an Electrical Installation Certificate (EIC) to BS 7671 for a rewire or consumer-unit replacement, and a Building Regulations compliance certificate when the work is notified through the scheme. A Minor Electrical Installation Works Certificate is only for certain alterations to an existing circuit, not for a full rewire. Ask for the certificates in writing before work starts.
Related reading
- House rewiring in Stockport & Manchester
- How can I tell if my house needs rewiring?
- Full rewire, partial rewire or just a new fuse box?
- Can you live in your home during rewiring?
- Will my walls need to be chased when rewiring?
- House rewire cost: what changes the price
Book a free survey
Want a straight answer for your home? We’ll arrange a free survey, or call 01253 364029 (Monday to Friday). Email office@fcrelectrical.co.uk. See our house rewire page to book a quote visit.